The project is located in Dongming Petrochemical Industrial Park,
with a total investment of 11.07 billion yuan and a total area of 93.24
hectares. The main construction is 300kt/a UPC test device, 100kt/a butadiene
extraction device, 8/ 50,000 tons/year MTBE/ butene-1 device, 550kt/a young
aromatics hydrogenation device, 350kt/a aromatics extraction device. As well as
supporting power station, circulating water, power transformation and
distribution, storage and transportation tank area and other auxiliary
engineering and public engineering facilities. Annual processing of crude oil
1.06 mt/a.
The technology has the advantages of low energy consumption, high
yield and short process, and can reduce crude oil consumption by about 60%
compared with the traditional "integrated refining and chemical"
process to produce the same scale of ethylene.
Dongming Petrochemical 300kt/a UPC project
2024 05/10