The investment amount of this project is 244.44 million yuan.
Nangang Ethylene Project is a representative project of Sinopec
Nangang high-end new materials industry project cluster. The project takes 1.2
mt/a ethylene plant as the leader and extends downstream along C2 and C3
product chain. Including 1.2 mt/a ethylene device, 150kt/a butadiene device,
500kt/a cracked gasoline hydrogenation device, 300kt/a aromatic extraction
device, 500kt/a HDPE device, 300kt/a LLDPE device, 100kt/a ultra-high molecular
weight polyethylene (UHMEP) E) Device, 100kt/a polyolefin elastomer (POE)
device, 200kt/a alpha-olefin (LAO) device, 130kt/a acrylonitrile device,
300kt/a PP device, 300kt/a acrylonitrile butadiene styrene resin (ABS) device,
and supporting the construction of necessary public works and auxiliary
facilities.
Tianjin Nangang 1.2 mt/a ethylene project
2024 04/12