Recently, China National Petroleum Corporation Jilin Petrochemical Company launched a 100-day critical campaign for the civil engineering work of its transformation and upgrading project, involving a 300,000 tons per annum (kt/a) tubular EVA plant and a 100,000 tons per annum autoclave EVA plant.This plant serves as the core facility for ethylene feedstock balance of Jilin Petrochemical.
At the construction site of the EVA Project under the Calcium Carbide Plant, the foundation construction for two sets of compressors has been fully completed. The steel bar binding and formwork erection work for the reactor explosion-proof dam foundation is advancing steadily.
Construction on non-critical routes is being pressed ahead simultaneously. Foundation trenching for supporting facilities including the 66kV substation, cabinet room and silo frame has been basically finished, with subsequent construction procedures such as steel bar binding and formwork erection initiated one after another. The construction site presents a sound development momentum with multi-point progress and coordinated advancement.
Up to now, a total of 7,260 foundation piles have been completed in the civil works, achieving a completion rate of 98%; the installation of main underground pipelines has finished 10,302 meters, with a 100% completion rate.